Accessing Property

Any entry or construction activities on railroad right of way must be authorized by the railroad in writing. Written authorization is obtained through a Right of Entry Permit or Contractor Occupancy/Access Agreement. The application is accessible via the link provided below.

The applicant must submit the completed application to the Real Estate Department including a check or money order, to cover the non-refundable fee of $1,500 made payable to the Railroad. The application must include railroad milepost, railroad subdivision, and scope of work. If any of these items on the application are incomplete, the application will be immediately rejected.

The standard term for a Right of Entry Permit or Contractor Occupancy/Access Agreement is sixty (60) days. Longer terms are reviewed on a case by case basis and may be assessed additional fees.

Upon approval of the application, the Real Estate Department will draft an agreement and forward to the applicant for signature. Application does not guarantee approval. The applicant must then return the signed document to the Real Estate Department along with the pertinent certificate of insurance outlined in the agreement. Once in receipt of these documents, the agreement will then be executed on behalf of the Railroad.

For "standard processing", the entire process takes between 6-8 weeks.  "Expedited processing" will reduce the processing time to between 1-2 weeks and costs an additional $1,750.  If the application and plans require engineering approval, and are returned to applicant for revisions in order to meet required specifications the expedited process could take longer than 2 weeks.

For any questions about Right of Entry permits please contact: 

Donna Killingsworth - Real Estate Manager at 904-900-6286 - gwappseast@gwrr.com or

Crystal Galbreath - Real Estate Coordinator at 904-596-7782 - gwappswest@gwrr.com  


Documents

ROE Application

Railroad Protective Liability Insurance Application